Termite Barriers
Purpose
Outline our process for installing chemical termite barriers using approved products (e.g., fipronil such as Termidor or equivalent). Always follow the current APVMA-approved label and SDS. Mixing rates, application volumes, and trench/drill specifications must match the label and site conditions.
- Scheduling & Labour
- Tools, PPE & Safety
- Site Prep & Utilities
- Measurement & Volume Planning
- Trenching Application (Soil)
- Drill & Inject (Concrete/Pavers)
- Weep Holes, Expansion Joints & Wet Areas
- Backfill, Make-Good & Colour Match
- Mixing, Transport & Waste
- Quality Checks & Handover
- Admin: ServiceM8 & Teams
Scheduling & Labour
- Time allowance: ~1 hour per 10 lineal metres for basic trenching. Extra time for heavy drilling.
- Jobs over 60 lineal metres: allocate an additional labourer or second tech.
- Confirm access, water source, power, parking, and noise windows with client.
Tools, PPE & Safety
- PPE per label/SDS: gloves, eye protection, respirator if required, protective clothing, safety boots.
- Tools: trenching shovel, injection rods, drill/hammer drill, bits, plugs/caps, mortar + colour tints, measuring wheel, mixing tank/pump, spill kit, wet/dry vacuum.
- Establish exclusion zones; prevent runoff to drains/waterways; use bunds where necessary.
Site Prep & Utilities
- Confirm services (power, water, gas, data). Dial-before-you-dig records if required.
- Mark injection points and trench lines. Photograph pre-start.
- Advise client of noise, dust, and access needs. Protect adjacent surfaces.
Measurement & Volume Planning
- Measure lineal metres (LM) of perimeter to treat; note construction types (soil, concrete, pavers, tiles).
- Calculate total solution volume per label: target volume per LM × total LM.
- Prepare sufficient product concentrate for expected total volume; keep batch/lot details.
Trenching Application (Soil)
- Excavate trench to depth/width as specified by the product label for the structure and soil type.
- Apply mixed chemical evenly to achieve label-specified application volume/LM and soil return saturation.
- Backfill in layers, treating each layer per label to maintain a continuous treated zone.
- Avoid pooling; ensure drainage away from stormwater inlets.
Drill & Inject (Concrete/Pavers)
- Mark drill line along slab edge/expansion joints to label specification. Confirm utilities below.
- Drill holes at label-specified spacing and diameter; vacuum dust; prevent dust from entering interiors.
- Inject to achieve target volume per hole/LM; monitor for refusal/leakage and adjust technique.
- Plug holes with caps or mortar; match mortar colour to existing as closely as practical.
Weep Holes, Expansion Joints & Wet Areas
- Weep holes: Do not block. Follow label on proximity and application method.
- Wet areas: Isolate stormwater sumps/pits; prevent chemical entry; use barriers if needed.
- Joints/penetrations: Ensure continuity around pipes, steps, and construction joints.
Backfill, Make-Good & Colour Match
- Restore soils, pavers, and concrete finishes neatly. Wash down work areas.
- Mortar/plug finish should be flush and colour-matched where feasible.
- Remove debris; leave site clean and safe.
Mixing, Transport & Waste
- Mix strictly to label directions using clean water and calibrated equipment.
- Never exceed or under-dose. Record batch/lot and volumes used.
- Transport/store chemicals upright, in bunded areas. Dispose of rinsate/empties per label and local regulations.
Quality Checks & Handover
| Check | Acceptable Standard |
|---|---|
| Continuity | Unbroken treated zone; correct volumes documented |
| Finish | Clean, holes plugged, mortar colour matched |
| Safety | No runoff; signage used if needed; PPE worn |
| Client briefing | Explain what was done, product used, warranty/monitoring |
Admin: ServiceM8 & Teams
- Update ServiceM8 with measurements, volumes, product, lot/batch, photos (before/after), drawings.
- Attach compliance docs (label/SDS if required) and client handouts.
- Post completion note and photos in Teams project/channel if requested.